Sweet-Dreams Inc. manufactures custom pillows. Five jobs are waiting to be processed. Job A has a flow time of 8 days, job B has a flow time of 10 days, job C has a flow time of 15 days, job D has a flow time of 20 days, and job E has a flow time of 27 days. What is the mean flow time?
a) 8 days
b) 10 days
c) 7 days
d) 0 days
e) 16 days
e) 16 days
Solution: 8+10+15+20+27=80/5=16