If the third stage of a repetitive line process cannot complete its activities as fast as stage one or two it has become a:
a) key work location
b) bottle neck
c) place not to work
d) project process location
e) none of these
Answer: b
Marketing MCQ
a) key work location
b) bottle neck
c) place not to work
d) project process location
e) none of these
Answer: b