The process of calculating ES and EF _______________.

The process of calculating ES and EF _______________.



a) requires only a forward pass through the network

b) requires only a backward pass through the network

c) requires both a forward and backward pass through the network

d) cannot be accomplished until slack is first determined

e) is sufficient for calculating the critical path



Answer: a