If the schedule shows a 5 day slack between the end of Task A and start of Task B, this means:

If the schedule shows a 5 day slack between the end of Task A and start of Task B, this means:



a) you must start Task B as soon as Task A ends.
b) Task B start is late.
c) Task A is taking longer to complete.
d) Task A and Task B should be performed concurrently.
e) Task B start can be delayed up to 5 days after Task A's scheduled completion.


Answer: e) Task B start can be delayed up to 5 days after Task A's scheduled completion.