In calculating the estimated probability of completion value a negative number is obtained. This means:

In calculating the estimated probability of completion value a negative number is obtained. This means:



a) your calculation is wrong.

b) the project will be delayed.

c) the specified completion time is later than the expected completion time.

d) the specified completion time is earlier than the expected completion time.

e) the variance is incorrect.



Answer: d