In making a backward pass through a network, activity L has an activity time of 4 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M, P, and T are 29, 27, and 33, respectively. What is the late finish time for activity L?

In making a backward pass through a network, activity L has an activity time of 4 and immediately precedes activities M, P, and T. The late start times for activities M, P, and T are 22, 17, and 27, respectively. The late finish times for activities M, P, and T are 29, 27, and 33, respectively. What is the late finish time for activity L?



a) 13

b) 17

c) 22

d) 33

e) 37



Answer: b


Learn More :