Joe's radio tower fabrication company has developed the following milestone project schedule. What is the expected time duration for the project?

Joe's radio tower fabrication company has developed the following milestone project schedule. What is the expected time duration for the project?


ACTIVITY PRECEDENCE P M O

A Complete design None 4 3 2

B Develop BOM A 2 1 1

C Order Materials B 3 2 1

D Site Selection A 7 4 3

E Receive Materials C 6 3 2

F Obtain permits A, D 4 2 1

G Begin fabrication facility development E, F 6 5 3


a) 9

b) 10

c) 14

d) 14.33

e) 17.33

f) 21



Answer: d