The formula to calculate an activity's probabilistic expected time is
a) ET = ( M+4*O+P)/6
b) ET = ( P+4*O+M)/6
c) ET = ( P+4*M+O)/6
d) ET = ( P+3*M+O)2/6
e) ET = ( M+3*O+P)/4
Answer: c
Marketing MCQ
a) ET = ( M+4*O+P)/6
b) ET = ( P+4*O+M)/6
c) ET = ( P+4*M+O)/6
d) ET = ( P+3*M+O)2/6
e) ET = ( M+3*O+P)/4
Answer: c