Removing safety time from the individual activities and putting the total safety time at the end of the critical path creates a(n) ___________________.

Removing safety time from the individual activities and putting the total safety time at the end of the critical path creates a(n) ___________________.



a) project safety net

b) project buffer

c) overconfident project manager

d) activity shortage

e) larger number of activities



Answer: b