Given this information about an activity: ES = 10, EF = 15, LS = 26, and LF = 31. The amount of slack associated with the activity is _________.
Given this information about an activity: ES = 10, EF = 15, LS = 26, and LF = 31. The amount of slack associated with the activity is _________.
Given this information about an activity: ES = 10, EF = 15, LS = 26, and LF = 31. The amount of slack associated with the activity is _________.
a) 32
b) 5
c) 21
d) 16
e) 11
Answer: d