Given this information about an activity: ES = 10, EF = 18, LS = 28, and LF = 36. The amount of slack associated with the activity is ____________________.
Given this information about an activity: ES = 10, EF = 18, LS = 28, and LF = 36. The amount of slack associated with the activity is ____________________.
Given this information about an activity: ES = 10, EF = 18, LS = 28, and LF = 36. The amount of slack associated with the activity is ____________________.
a) 38
b) 8
c) 18
d) 26
e) 10
Answer: c