Given this information about an activity: ES = 10, EF = 20, LS = 29, and LF = 39. The amount of slack associated with the activity is ____________________.

Given this information about an activity: ES = 10, EF = 20, LS = 29, and LF = 39. The amount of slack associated with the activity is ____________________.



a) 29

b) 9

c) 19

d) 38

e) 10



Answer: c