Which of the following can be calculated for an activity once ES, EF, LS, and LF have been calculated for the activity?

Which of the following can be calculated for an activity once ES, EF, LS, and LF have been calculated for the activity?



a) expected project duration

b) slack time

c) potential for crashing

d) variance in project duration

e) the relative time position for when the activity will be completed



Answer: b


Learn More :

Marketing Supply Chain

Learn More Multiple Choice Question :