In making a backward pass through a network, activity T immediately precedes three activities. What is the late finish time for activity T?

In making a backward pass through a network, activity T immediately precedes three activities. What is the late finish time for activity T?



a) the smallest LS for the three activities that activity T immediately precedes

b) the largest LS for the three activities that activity T immediately precedes

c) the smallest LF for the three activities that activity T immediately precedes

d) the largest LF for the three activities that activity T immediately precedes

e) the activity time for activity T



Answer: a