Which of the following information about activities is not needed in determining how to crash a project?

Which of the following information about activities is not needed in determining how to crash a project?



a) the normal cost

b) the crash cost

c) the crash time estimate

d) the normal time estimate

e) how many dummy activities there are



Answer: e