Which of the following is not included in the approach for crashing projects?
a) Determine which activity requires the most time.
b) Crash the least expensive activity first.
c) Determine how much the project needs to be reduced.
d) Calculate the total costs associated with crashing the project.
e) Determine which activities on the critical path can be reduced.
Answer: a