Each day for two workweeks (10 days total), George weighs 4 bags from that day's production. If the average of the means is 14 oz. and the average range is 0.4 oz., what is the lower control limit for an x-bar chart for this process?

Each day for two workweeks (10 days total), George weighs 4 bags from that day's production. If the average of the means is 14 oz. and the average range is 0.4 oz., what is the lower control limit for an x-bar chart for this process?



a) 13.7084 oz.

b) 13.8768 oz.

c) 14.2916 oz.

d) 12.8000 oz.

e) 13.5908 oz.



Answer: a