Each day for two workweeks (10 days total), George weighs 4 bags from that day's production. If the average of the means is 14 oz. and the average range is 0.4 oz., what is the lower control limit for an x-bar chart for this process?
Each day for two workweeks (10 days total), George weighs 4 bags from that day's production. If the average of the means is 14 oz. and the average range is 0.4 oz., what is the lower control limit for an x-bar chart for this process?
Each day for two workweeks (10 days total), George weighs 4 bags from that day's production. If the average of the means is 14 oz. and the average range is 0.4 oz., what is the lower control limit for an x-bar chart for this process?
a) 13.7084 oz.
b) 13.8768 oz.
c) 14.2916 oz.
d) 12.8000 oz.
e) 13.5908 oz.
Answer: a