If a delay in an activity will delay completion of the whole project, the activity ____________________.

If a delay in an activity will delay completion of the whole project, the activity ____________________.



a) is on the critical path

b) has slack

c) is costly

d) is a dummy

e) is represented by a node



Answer: a