The probability of completing a project in a specified amount of time is being calculated. For a particular path through the project, the ______________ shows the path's number of standard deviations that the specified time is past the expected path completion time.

The probability of completing a project in a specified amount of time is being calculated. For a particular path through the project, the ______________ shows the path's number of standard deviations that the specified time is past the expected path completion time.



a) m-value

b) z-value

c) sigma-value

d) s-value

e) alpha-value



Answer: b