The probability of completing a project in a specified amount of time is being calculated. For a particular path through the project, the ______________ shows the path's number of standard deviations that the specified time is past the expected path completion time.
The probability of completing a project in a specified amount of time is being calculated. For a particular path through the project, the ______________ shows the path's number of standard deviations that the specified time is past the expected path completion time.
The probability of completing a project in a specified amount of time is being calculated. For a particular path through the project, the ______________ shows the path's number of standard deviations that the specified time is past the expected path completion time.
a) m-value
b) z-value
c) sigma-value
d) s-value
e) alpha-value
Answer: b