There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. The standard deviation of the critical path is ______.
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. The standard deviation of the critical path is ______.
There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. The standard deviation of the critical path is ______.
a) 3
b) 5
c) 9
d) 16
e) 25
Answer: b