There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. The standard deviation of the critical path is ______.

There are four activities on the critical path, and they have standard deviations of 1, 2, 4, and 2. The standard deviation of the critical path is ______.



a) 3

b) 5

c) 9

d) 16

e) 25



Answer: b