Which of the following is not a benefit of network planning techniques?

Which of the following is not a benefit of network planning techniques?



a) graphical display of the project, including the relationships and sequence of activities

b) estimate of the expected project length

c) resources are clearly identified

d) identification of activities that are critical to the timely completion of the project

e) identification of the amount of slack associated with individual activities



Answer: c