Job A is due on day 15, and it is finished on day 12. What is its lateness?

Job A is due on day 15, and it is finished on day 12. What is its lateness?



a) -3
b) 0
c) 3
d) both -3 and 3
e) none of these answer choices are correct


Answer: a) -3

Solution: 15-12 = 3; ahead of schedule